ATL-2401ActiveOn Track

Skyline Tower — HVAC Installation

Full mechanical HVAC installation across 34 floors including chilled water plant, AHUs, and BMS integration.

Munich, DE04 Nov 202530 Sept 2026€1.5M of €2.5MAegis Construction Group
Progress62%
x

62% budget burned

Project metadata

Code
ATL-2401
Category
HVAC
Location
Munich, DE
Start
04 Nov 2025
Due
30 Sept 2026
Client
Aegis Construction Group

Partners & suppliers

4 organisations

Recent meeting logs

  • AHU Vendor Technical Alignment

    03 Mar 2026

    Supplier Review

    Reviewed acoustic performance and BMS integration scope. Meridian to confirm sound attenuator selection and revise commissioning allowance.

  • Weekly Client Progress — Aegis

    26 Feb 2026

    Client Call

    Presented 62% progress. Client raised concern on level 12 duct clash. Agreed on recovery plan; no cost impact expected.

Financial summary

Quoted

€2,450,000

Contract budget

Actual cost

€1,512,000

3 invoices posted

Variance

€938,000

38% remaining vs quote

Assigned team

  • Ahmet Yilmaz

    Lead Engineer

  • Sofia Lindqvist

    Procurement Manager

  • Elena Rossi

    CAD Specialist